Last Updated: 01 April 2024
'Buddha river' is a seasonal water stream, which runs through the Malwa region of Punjab and after passing through the highly populated Ludhiana district, it drains into Sutlej River
It is now called 'Buddha nullah' i.e. Buddha Drain, due to previous Govt negligence
TARGET: Stream to regain its glory from being called as 'Nullah' (Drain) to be called as Buddha 'Dariya'(River)

- Total estimated cost: ₹825 crores
- Dec 2023: 95% completion with ₹538.55 crores already spent
- Operation & maintenance: ₹294 crores would be spent for another 10 years after completion
- Punjab government is spending ₹392 crore whereas the central government is giving a grant of ₹258 crore
2 New sewage treatment plants(STPs)
- To handle Domestic Waste
- 225 MLD capacity at Jamalpur
- The biggest such facility in Punjab, inaugurated by CM Bhagwant Mann on 21 Feb 2023
- 60-MLD capacity at Balloke
6 New intermediate pumping stations(IPS)
- 12-MLD capacity at Tibba
- 8-MLD capacity at Sundar Nagar
- 5-MLD capacity IPS at Kundanpuri
- 13-MLD capacity at Upkar Nagar
- 13-MLD capacity at Upkar Nagar
- LMH IPS
- another IPS near gaushala
Repair of existing STPs & MPS(pumping stations)
- Total 418 MLD treatment capacity
- 105-MLD capacity at Balloke
- 50-MLD capacity at Bhattian
- 111-MLD capacity at Bhattian
- 152-MLD capacity at Balloke
Industrial effluent discharge
- Total 137 MLD was discharge into the nullah
- All industrial units have been connected to common effluent treatment plants(CETPs) or their own Effluent treatment plants
- 3 CETPs had been installed recently
- 50-MLD on Jail Road for Tajpur Road
- 40-MLD capacity in Focal Point area industries
- 15-MLD capacity on Bahadurke Road
Dairy waste management
- 2 ETPs for handling liquid waste from the dairy complex
- 3.75-MLD capacity ETP at Haibowal
- 2.25-MLD capacity plant on Tajpur Road
Laying of pipeline
- 6,475 m on the west side
- 4,944 m on east side
- 650 m from Kundanpuri to Upkar Nagar.
Author: @NAkilandeswari